Contract No.

1631

 

Owner / Developer

MTR Corporation Limited

 

Engineer

MTR Corporation Limited

 

Location and Project

The works mainly comprise ground investigation from Kwu Tung Station to Ngau Tam Mei Station for Northern Link. The investigation stations are located in villages, government lots, natural terrains and wetlands. The works were commenced in May 2021 and took about 46 months to complete.

 

Scope of Works

The ground investigation includes rotary drilling, environmental drilling, trial pitting, soil and rock sampling, in-situ testing and geophysics. To facilitate the geotechnical investigation, timber scaffolding and helicopter lifting will be deployed in the project. Besides the geotechnical investigation, non-destructive underground utilities survey and laboratory testing are included in the scope.

 

Year of Completion

2025

GROUND INVESTIGATION

Ground Investigation for Northern Link (North)