Contract No.

3303 & 3713

 

Owner / Developer

Hong Kong International Airport

 

Engineer

AECOM

 

Location and Project

The works mainly comprise ground investigation for the airport third runway associated works, concourse and infrastructures. The works were commenced in February 2020 and took about 13 months to complete.

 

Scope of Works

The ground investigation work includes rotary drilling and in-situ testing. Drillholes were extended to a maximum depth of 130m. In-situ testing including Acoustic Televiewers, Permeability, Vane Shear and Pressuremeter tests were carried out.

 

Year of Completion

2021

GROUND INVESTIGATION

Hong Kong International Airport Third Runway and Associated Works