Contract No.

81101111440

 

Owner / Developer

Hong Kong Hospital Authority 

 

Engineer

Hong Kong Hospital Authority 

 

Location and Project

The works mainly comprise ground investigation for the redevelopment of Kwong Wah Hospital (Phase 2). The works were commenced in October 2023 and will take about 24 months to complete.

 

Scope of Works

The ground investigation work includes rotary drilling and in-situ testing. Drill rigs and portable drill tools were used under different site conditions. The drillholes were located on flat ground and multiple floors inside the old buildings. Drilling and samplings were extended to a maximum depth of 80m. In-situ testing including Acoustic Televiewers, Permeability, Vane Shear and Packer Tests were carried out. Piezometers and standpipes were installed to monitor the underground water level within site boundary. 

 

Year of Completion

In Progress

GROUND INVESTIGATION

Demolition, Foundation, Superstructure and Associated Works Contract for Redevelopment of Kwong Wah Hospital (Phase 2)