Contract No.
HY/2019/13
Owner / Developer
Highways Department
Engineer
Ove Arup & Mott McDonald Joint Venture
Location and Project
The works mainly comprise ground investigation for the Central Kowloon Route. The works were commenced in October 2020 and took about 18 months to complete.
Scope of Works
The ground investigation work includes rotary drilling. Drilling and samplings were extended to a maximum depth of 100m. In-situ testing including Standard Penetration Test and Permeability Test were carried out. Piezometers and standpipes were installed to monitor the underground water level within site boundary.
Year of Completion
2022